RS Aggarwal solution class 8 chapter 13 Time and Work Exercise 13B

Exercise 13B

Page-174

Q1 | Ex-13B | Class 8 | RS AGGARWAL | chapter 13 | Time and Work | myhelper

Question 1:

Tick (✓) the correct answer:
A alone can do a piece of work in 10 days and B alone can do it in 15 days. In how many days will A and B together do the same work?
(a) 5 days
(b) 6 days
(c) 8 days
(d) 9 days

Answer 1:

(b) 6 days

A can do a work in 10 days.A's 1 day work = 110B can do a work in 15 days.B's 1 day work = 115(A+B)'s 1 day work = 110+115=530=16A and B together will take 6 days to complete the work.


Q2 | Ex-13B | Class 8 | RS AGGARWAL | chapter 13 | Time and Work | myhelper

Question 2:

Tick (✓) the correct answer:
A man can do a piece of work in 5 days. He and his son working together can finish it in 3 days. In how many days can the son do it alone?
(a) 612 days
(b) 7 days
(c) 712 days
(d) 8 days

Answer 2:

(c) 712 days

A man can do a work in 5 days.The man's 1 day work = 15The man and the son can do the work in 3 days.The man and his son's 1 day work =13Let the son's 1 day work be 1x.Therefore,13=15+ 1xor, 1x=13-15=5-315=215x = 152 = 712 days


Q3 | Ex-13B | Class 8 | RS AGGARWAL | chapter 13 | Time and Work | myhelper

Question 3:

Tick (✓) the correct answer:
A can do a job in 16 days and B can do the same job in 12 days. With the help of C, they can finish the job in 6 days only. Then, C alone can finish it in
(a) 34 days
(b) 22 days
(c) 36 dyas
(d) 48 days

Answer 3:

(d) 48 days

A can do a job in 16 days.B can do the job in 12 days.Suppose C can do the job in x days.A's 1 day work = 116B's 1 day work = 112C's 1 day work = 1xA, B and C together can complete the work in 6 days.(A+B+C)'s 1 day work = 16Therefore, 16=116+112+1x1x=16-116-112=8-3-448=148x = 48Therefore, C alone can complete the job in 48 days.


Q4 | Ex-13B | Class 8 | RS AGGARWAL | chapter 13 | Time and Work | myhelper

Question 4:

Tick (✓) the correct answer:
To complete a work, A takes 50% more time than B. If together they take 18 days to complete the work, how much time shall B take to do it?
(a) 30 days
(b) 35 days
(c) 40 days
(d) 45 days

Answer 4:

(a) 30 days

Let Btake x days to complete the work.Then A takes x+50100x=1.5xA's 1 day's work = 11.5x = 23xB's 1 day's work = 1x(A+B)takes 18 days to complete the work.(A+B)'s 1 day's net work = 118or 118=23x+1x118=53xBy cross-multiplication, we get:x=30 days B alone will take 30 days to complete the work.


Q5 | Ex-13B | Class 8 | RS AGGARWAL | chapter 13 | Time and Work | myhelper

Question 5:

Tick (✓) the correct answer:
A works twice as fast as B. If both of them can together finish a piece of work in 12 days, then B alone can do it in
(a) 24 days
(b) 27 days
(c) 36 days
(d) 48 days

Answer 5:

(c) 36 days

Let A take x days to complete the work. 

Then B takes 2x days to complete the work.

A's 1 day's work=1xB's 1 day's work=12xA and B take 12 days to complete the work.

Net work done by (A+B) in 1 day=112=1x+12x=32x2x=36x=18A can complete the work by himself in 18 days.

B will take 36 days, i.e., twice as long as the time taken by A. 


Q6 | Ex-13B | Class 8 | RS AGGARWAL | chapter 13 | Time and Work | myhelper

Question 6:

Tick (✓) the correct answer:
A alone can finish a piece of work in 10 days which B alone can do in 15 days. If they work together and finish it, then out of total wages of Rs 3000, A will get
(a) Rs 1200
(b) Rs 1500
(c) Rs 1800
(d) Rs 2000

Answer 6:

(c) Rs. 1800

Since the wage distribution will follow the work distribution ratio, we have:

Work done by A in 1 day =110
Work done by B in 1 day =115

Net work done by (A+B) in 1 day =110+115=530=16

i.e., (A+B) will take 6 days to complete the work.

A's share of work in a day = 110÷16=110×61=610=35

∴ A's wage = 35×3000=Rs 1800


Q7 | Ex-13B | Class 8 | RS AGGARWAL | chapter 13 | Time and Work | myhelper

Question 7:

Tick (✓) the correct answer:
The rates of working of A and B are in the ratio 3 : 4. The number of days taken by them to finish the work are in the ratio
(a) 3 : 4
(b) 9 : 16
(c) 4 : 3
(d) 16 : 9

Answer 7:

(c) 4:3

The number of days taken for working is the reciprocal of the rate of work.

i.e., number of days taken =1rate of work=134=43


Q8 | Ex-13B | Class 8 | RS AGGARWAL | chapter 13 | Time and Work | myhelper

Question 8:

Tick (✓) the correct answer:
A and B together can do a piece of work in 12 days; B and C can do it in 20 days while C and A can do it in 15 days. A, B and C all working together can do it in
(a) 6 days
(b) 9 days
(c) 10 days
(d) 1012 days

Answer 8:

(c) 10 days

(A+B) can do a work in 12 days.(B+C) can do a work in 20 days.(C+A)can do a work in 15 days.Now, we have:Work done by (A+B) in 1 day = 112Work done by (B+C) in 1 day = 120Work done by (C+A) in 1 day = 115Net work done by 2(A+B+C) = 112+120+115=5+3+460=1260=15Net work done by (A+B+C)  in 1 day=110If A, B and C work together, they will complete the work in 10 days.

Q9 | Ex-13B | Class 8 | RS AGGARWAL | chapter 13 | Time and Work | myhelper

Question 9:

Tick (✓) the correct answer:
3 men or 5 women can do a work in 12 days. How long will 6 men and 5 women take to do it?
(a) 6 days
(b) 5 days
(c) 4 days
(d) 3 days

Answer 9:

(c) 4 days

Three men can complete the work in 12 days.Thus, one man can complete the work in 36 days.Rate of work done by one man in 1 day =136Similarly, rate of work done by one woman in 1 day = 15×12=160 Now, six men will do 636, i.e., 16 unit of work in a day.Five women will do 560, i,e., 112unit of work in a day. Total work done in 1 day= 16+112 = 14 unit 

Thus, six men and five women will take 4 days to complete the work.

The work can be completed in 4 days.


Q10 | Ex-13B | Class 8 | RS AGGARWAL | chapter 13 | Time and Work | myhelper

Question 10:

Tick (✓) the correct answer:
A can do a piece of work in 15 days. B is 50% more efficient than A. B can finish it in
(a) 10 days
(b) 712 days
(c) 12 days
(d) 1012 days

Answer 10:

(a) 10 days

Work done by A in 1 day=115B is 50% more efficient than A.  Work done by B in 1 day=150100×115=110Thus, B can complete the work in 10 days.


Page-175

Q11 | Ex-13B | Class 8 | RS AGGARWAL | chapter 13 | Time and Work | myhelper

Question 11:

Tick (✓) the correct answer:
A does 20% less work than B. If A can finish a piece of work in 712 hours, then B can finish it in
(a) 5 hours
(b) 512 hours
(c) 6 hours
(d) 612 hours

Answer 11:

(c) 6 hours

Time taken by A to finish the piece of work=712 hours=152 hoursWork done by A in 1 hour=215Let B take x hours to finish the work.Work done by B in 1 hours=1xA can work 20%less than B, or A can do 45 of B's work.

Now, 451=2151x45=2x15x=15×45×2=6 hours


Q12 | Ex-13B | Class 8 | RS AGGARWAL | chapter 13 | Time and Work | myhelper

Question 12:

Tick (✓) the correct answer:
A can do a piece of work in 20 days which B alone can do in 12 days. B worked at it for 9 days. A can finish the remaining work in
(a) 3 days
(b) 5 days
(c) 7 days
(d) 11 days

Answer 12:

(b) 5 days

A can complete the work in 20 days.Work done by A in 1 day=120B can complete the work in 12 days.Work done by B in 1 day=112In 9 days, B completes 912, i.e., 34 of the work and leaves 1-34, i.e., 14 of the work undone. Time taken by A=14÷120=14×20=5 days


Q13 | Ex-13B | Class 8 | RS AGGARWAL | chapter 13 | Time and Work | myhelper

Question 13:

Tick (✓) the correct answer:
A can do a piece of work in 25 days, which B alone can do in 20 days. A started the work and was joined by B after 10 days. The work lasted for
(a) 1212 days
(b) 15 days
(c) 1623 days
(d) 14 days

Answer 13:

(c) 

A can do the piece of work in 25 days.

Work done by A in 1 day=125B can do the same work in 20 days.

Work done by B in 1 day=120A alone completes 1025, i,e., 25 of the work in 10 days. 

Now, work remaining =1-25=35 

Work done by (A+B) in 1 day=125+120=9100 

 Time taken if they work together=35÷9100=35×1009=203=623 days


Q14 | Ex-13B | Class 8 | RS AGGARWAL | chapter 13 | Time and Work | myhelper

Question 14:

Tick (✓) the correct answer:
Two pipes can fill a tank in 20 minutes and 30 minutes respectively. If both the pipes are opened simultaneously, then the tank will be filled in
(a) 10 minutes
(b) 12 minutes
(c) 15 minutes
(d) 25 minutes

Answer 14:

(b) 12 minutes

First pipe can fill a tank in 20 minutes.

Second pipe can fill the tank in 30 minutes.

Part of tank filled by the first pipe in one minute = 120

Part of tank filled by the second pipe in one minute 130 

Part of tank filled by both pipes in one minute = 120+130=560=112 

Thus, it takes 12 minutes to fill the tank using both the pipes.


Q15 | Ex-13B | Class 8 | RS AGGARWAL | chapter 13 | Time and Work | myhelper

Question 15:

Tick (✓) the correct answer:
A tap can fill a cistern in 8 hours and another tap can empty the full cistern in 16 hours. If both the taps are open, the time taken to fill the cistern is
(a) 513 hours
(b) 10 hours
(c) 16 hours
(d) 20 hours

Answer 15:

(c) 16 hours

A tap can fill a cistern in 8 hours.Part of cistern filled in one hour = 18A tap can empty the cistern in 16 hours.Part of cistern emptied in one hour =- 116 (negative sign shows that the cistern is being drained) Part of cistern filled in one hour = 18-116=116Time required to fill the cistern = 16 hours


Q16 | Ex-13B | Class 8 | RS AGGARWAL | chapter 13 | Time and Work | myhelper

Question 16:

Tick (✓) the correct answer:
A pump can fill a tank in 2 hours. Due to a leak in the tank it takes 213 hours to fill the tank. The leak can empty the full tank in
(a) 213 hours
(b) 7 hours
(c) 8 hours
(d) 14 hours

Answer 16:

(d) 14 hours

A pump can fill a tank in 2 hours.Part of the tank filled by the pump in one hour = 12Suppose the leak empties a full tank in x hours.Part of the tank emptied by the leak in one hour = -1xPart of tank filled in one hour = 12-1x=37  (given)1x=12-37=7-614=114x=14 hours


Q17 | Ex-13B | Class 8 | RS AGGARWAL | chapter 13 | Time and Work | myhelper

Question 17:

Tick (✓) the correct answer:
Two pipes can fill a tank in 10 hours and 12 hours respectively, while a third pipe empties the full tank in 20 hours. If all the three pipes operate simultaneously, in how much time will the tank be full?
(a) 7 hrs 15 min
(b) 7 hrs 30 min
(c) 7 hrs 45 min
(d) 8 hrs

Answer 17:

(b) 7 hours 30 minutes

Part of the tank filled by the first pipe in one hour = 110Part of the tank filled by the second pipe in one hour  = 112Part of the tank filled by the third pipe in one hour   = -120Part of the tank filled by three pipes in one hour  = 110+112-120 = 215Total time taken to fill the tank = 152hrs= 7 hours 30 minutes