RS Aggarwal solution class 8 chapter 13 Time and Work Exercise 13A

Exercise 13A

Page-172

Q1 | Ex-13A | Class 8 | RS AGGARWAL | chapter 13 | Time and Work | myhelper

Question 1:

Rajan can do a piece of work in 24 days while Amit can do it in 30 days. In how many days can they complete it, if they work together?

Answer 1:

Work done by Rajan in 1 day = 124Work done by Amit in 1 day = 130Work done by Amit and Rajan together in 1 day = 124+130=54720=340 They can complete the work in 403 days, i.e., 1313days if they work together.


Q2 | Ex-13A | Class 8 | RS AGGARWAL | chapter 13 | Time and Work | myhelper

Question 2:

Ravi can do a piece of work in 15 hours while Raman can do it in 12 hours. How long will both take to do it, working together?

Answer 2:

Time taken by Ravi = 15 hTime taken by Raman = 12 hWork done per hour by Ravi = 115Work done per hour by Raman = 112Work done per hour by Ravi and Raman together = 115+112=960=320 Time taken by Ravi and Raman together to finish the work = 203 h = 623 h


Q3 | Ex-13A | Class 8 | RS AGGARWAL | chapter 13 | Time and Work | myhelper

Question 3:

A and B, working together can finish a piece of work in 6 days, while A alone can do it in 9 days. How much time will B alone take to finish it?

Answer 3:

Time taken by A and B to finish a piece of work = 6 daysWork done per day by Aand B = 16Time taken by Aalone = 9 daysWork done per day by Aalone = 19Work done per day by B =(work done by A and B )-(work done by A)=16-19=3-218=118 B alone will take 18 days to complete the work.


Q4 | Ex-13A | Class 8 | RS AGGARWAL | chapter 13 | Time and Work | myhelper

Question 4:

Two motor mechanics, Raju and Siraj, working together can overhaul a scooter in 6 hours. Raju alone can do the job in 15 hours. In how many hours can Siraj alone do it?

Answer 4:

Time taken by Raju = 15 hWork done by Raju in 1 h =115Time taken by Raju and Siraj working together = 6 hWork done by Raju and Siraj in 1 h = 16Work done by Siraj in 1 h =(work done by Raju and Siraj) -(work done by Raju)=16-115=5-230=330=110 Siraj will take 10 h to overhaul the scooter by himself.


Q5 | Ex-13A | Class 8 | RS AGGARWAL | chapter 13 | Time and Work | myhelper

Question 5:

A, B and C can do a piece of work in 10 days, 12 days and 15 days respectively. How long will they take to finish it if they work together?

Answer 5:

Time taken by A to complete the work =10 daysTime taken by Bto complete the work = 12 daysTime taken by Cto complete the work = 15 daysWork done per day by A =110Work done per day by B=112Work done per day byC =115Total work done per day =110+112+115=6+5+460=1560=14A, B and Cwill take 4 days to complete the work if they work together.


Q6 | Ex-13A | Class 8 | RS AGGARWAL | chapter 13 | Time and Work | myhelper

Question 6:

A can do a piece of work in 24 hours while B alone can do it in 16 hours. If A, B and C working together can finish it in 8 hours, in how many hours can C alone finish the work?

Answer 6:

Time taken by A to complete the piece of work = 24 hWork done per hour by A = 124Time taken by B to complete the work = 16 hWork done per hour by B= 116Total time taken when A, B and C work together = 8 hWork done per hour by A, B and C=18Work done per hour by A, B and C =(work done per hour by A) + (work done per hour by B) + (work done per hour by C) (Work done per hour by C) =(work done per hour by A, B and C) - (work done per hour by A) - (work done per hour by B)=18-124-116=6-2-348=148Thus, C alone will take 48 h to complete the work.


Q7 | Ex-13A | Class 8 | RS AGGARWAL | chapter 13 | Time and Work | myhelper

Question 7:

A, B and C working together can finish a piece of work in 8 hours. A alone can do it in 20 hours and B alone can do it in 24 hours. In how many hours will C alone do the same work?

Answer 7:

A can complete the work in 20 h.Work done per hour by A=120B can complete the work in 24 h.Work done per hour by B=124It takes 8 h to complete the work if A, B and C work together.Work done together per hour by A, B and C=18(Work done per hour by A, B and C) =(work done per hour by A)+(work done per hour by B)+(work done per hour by C)OR(Work done per hour by C)=(work done per hour by A, B and C)-(work done per hour by A)-(work done per hour by B)=18-124-120=130 C alone will take 30 h to complete the work. 


Page-173

Q8 | Ex-13A | Class 8 | RS AGGARWAL | chapter 13 | Time and Work | myhelper

Question 8:

A and B can finish a piece of work in 16 days and 12 days respectively. A started the work and worked at it for 2 days. He was then joined by B. Find the total time taken to finish the work.

Answer 8:

Time taken by Ato complete the work = 16 daysWork done per day by A = 116Time taken by B to complete the work = 12 daysWork done per day by B = 112Work done per day by A and B = 112+116=4+348=748Work done by A in two days = 216=18Work left =1- 18=78A and B together can complete 748 of the work in 1 day.Then, time taken to complete 78 of the work = 78÷748=78×487 = 6 days Total time taken = 6 + 2 = 8 days.


Q9 | Ex-13A | Class 8 | RS AGGARWAL | chapter 13 | Time and Work | myhelper

Question 9:

A can do a piece of work in 14 days while B can do it in 21 days. They began together and worked at it for 6 days. Then, A fell ill and B had to complete the remaining work alone. In how many days was the work completed?

Answer 9:

Time taken by A to complete the work = 14 daysWork done by Ain one day = 114Time taken by B to complete the work = 21 daysWork done by B in one day = 121Work done jointly by A and B in one day =114+121=3 + 242=542Work done by A and B in 6 days = 542 × 6 =57Work left = 1-57=27With B working alone, time required to complete the work =27÷121=27 × 21 = 2 × 3 = 6 daysSo, the total time taken to complete the work = 6 + 6 = 12 days


Q10 | Ex-13A | Class 8 | RS AGGARWAL | chapter 13 | Time and Work | myhelper

Question 10:

A can do 23 of a certain work in 16 days and B can do 14 of the same work in 3 days. In how many days can both finish the work, working together?

Answer 10:

A can do 23 work in 16 daysSo, work done byA in one day = 248=124B can do 14 work in 3 daysSo, work done by B in one day =112Work done jointly by A and B in one day =124 + 112 = 1 + 224= 324 = 18So, A and B together will take 8 days to complete the work.


Q11 | Ex-13A | Class 8 | RS AGGARWAL | chapter 13 | Time and Work | myhelper

Question 11:

A, B and C can do a piece of work in 15, 12 and 20 days respectively. They started the work together, but C left after 2 days. In how many days will the remaining work be completed by A and B?

Answer 11:

Time taken by A = 15 daysTime taken by B = 12 daysTime taken by C = 20 daysWork d by A in one day =115Work done by B in one day = 112Work done by C in one day =120Work done in one day by A, B and C together=115+112+120=4+5+360=1260=15Work done by A, B and C together in 2 days =25Work remaining = 1-25=35Work done by A and B in one day =115+112=960=320Time required by A and B to complete the remaining work together = 35÷320=35×203= 4 days


Q12 | Ex-13A | Class 8 | RS AGGARWAL | chapter 13 | Time and Work | myhelper

Question 12:

A and B can do a piece of work in 18 days; B and C can do it in 24 days while C and A can finish it in 36 days. In how many days can A, B, C finish it, if they all work together?

Answer 12:

Time needed by A and B to finish the work =18 daysTime needed by B and C to finish the work =24 daysTime needed by C and A to finish the work =36 daysWork done by A and B in one day =118 Work done by B and C in one day =124 Work done by C and A in one day =136 2 × Work done by A, B and C in one day  = 118+124+136=4+3+272=972=18∴ Work done by A, B and C in one day = 116So, A, B andC working together will take 16 days to complete the work.


Q13 | Ex-13A | Class 8 | RS AGGARWAL | chapter 13 | Time and Work | myhelper

Question 13:

A and B can do a piece of work in 12 days, B and C in 15 days, and C and A in 20 days. How much time will A alone take to finish the job?

Answer 13:

(A+B) can complete the work in 12 days.(B+C)can complete the work in 15 days.(C+A) can complete the work in 20 days.(A+B)'s 1 day work = 112(B+C)'s 1 day work =115(C+A)'s 1 day work =1202(A+B+C)'s 1 day work =112+115+120=5+4+360=1260=15(A+B+C)'s 1 day work =110A's 1 day work = (A+B+C)'s 1 day work - (B+C)'s 1 day work = 110-115=3-230=130A will take 30 days to complete the work, if he works alone.


Q14 | Ex-13A | Class 8 | RS AGGARWAL | chapter 13 | Time and Work | myhelper

Question 14:

Pipes A and B can fill an empty tank in 10 hours and 15 hours respectively. If both are opened together in the empty tank, how much time will they take to fill it completely?

Answer 14:

A can fill a tank in 10 hours.B can fill a tank in 15 hours.Pipe A fills 110 of the tank in one hour.Pipe B fills 115of the tank in one hour.Part of tank filled by pipes A and B together = 110+115= 3 + 230= 530 = 16Thus, pipes A and B require 6 hours to fill the tank.


Q15 | Ex-13A | Class 8 | RS AGGARWAL | chapter 13 | Time and Work | myhelper

Question 15:

Pipe A can fill an empty tank in 5 hours while pipe B can empty the full tank in 6 hours. If both are opened at the same time in the empty tank, how much time will they take to fill it up completely?

Answer 15:

Pipe A can fill a tank in 5 hours.Pipe B can empty a full tank in 6 hours.Pipe A fills 15 of the tank in one hour.Pipe B empties 16 of the tank in one hour.Part of the tank filled in one hour using both pipes A and B =  15-16=6-530=130 It takes 301 or 30 hours to fill the tank completely.


Q16 | Ex-13A | Class 8 | RS AGGARWAL | chapter 13 | Time and Work | myhelper

Question 16:

Three taps A, B and C can fill an overhead tank in 6 hours, 8 hours and 12 hours respectively. How long would the three taps take to fill the empty tank, if all of them are opened together?

Answer 16:

Time taken by tap A to fill the tank = 6 hoursTime taken by tap B to fill the tank = 8 hoursTime taken by tap C to fill the tank = 12 hoursA fills 16 of the tank in one hour.B fills 18 of the tank in one hour.C fills 112 of the tank in one hour.Part of the tank filled in one hour using all the three pipes = 16+18+112 = 4+3+224 = 924Time taken by A, B and C together to fill the tank = 249=83=223 hours


Q17 | Ex-13A | Class 8 | RS AGGARWAL | chapter 13 | Time and Work | myhelper

Question 17:

A cistern has two inlets A and B which can fill it in 12 minutes and 15 minutes respectively. An outlet C can empty the full cistern in 10 minutes. If all the three pipes are opened together in the empty tank, how much time will they take to fill the tank completely?

Answer 17:

Inlet A can fill the cistern in 12 minutes.Inlet B can fill the cistern in 15 minutes.Outlet C empties the filled cistern in 10 minutes.Part of the cistern filled by inlet A in one minute = 112Part of the cistern filled by inlet B in one minute = 115Part of the cistern emptied by outlet C in one minute = -110 (water flows out from C and empties the cistern)Part of the cistern filled in one minute with A, B and C working together = 112+115-110=5+4-660=360=120The time required to fill the cistern with all inlets, A, B and C, open is 20 minutes.


Q18 | Ex-13A | Class 8 | RS AGGARWAL | chapter 13 | Time and Work | myhelper

Question 18:

A pipe can fill a cistern in 9 hours. Due to a leak in its bottom, the cistern fills up in 10 hours. If the cistern is full, in how much time will it be emptied by the leak?

Answer 18:

Apipe can fill a cistern in 9 hours.Part of the cistern filled by the pipe in one hour = 19Let the leak empty the cistern in x hours.Part of the cistern emptied by the leak in one hour = -1x (The leak drains out the water)Considering the leak, the tank is filled in 10 hours.Part of the tank filled in one hour = 110Therefore,19 - 1x=110 or,  1x=19-110=10-990=190x = 90

The leak will empty the filled cistern in 90 hours.


Q19 | Ex-13A | Class 8 | RS AGGARWAL | chapter 13 | Time and Work | myhelper

Question 19:

Pipe A can fill a cistern in 6 hours and pipe B can fill it in 8 hours. Both the pipes are opened and after two hours, pipe A is closed. How much time will B take to fill the remaining part of the tank?

Answer 19:

Pipe A can fill a cistern in 6 hours.Pipe B can fill a cistern in 8 hours.Part of the cistern filled by pipe A in one hour = 16Part of the cistern filled by pipe B in one hour = 18Part of the cistern filled by pipes A and B in one hour = 16+18=4+324=724Part of the cistern filled by pipes A and B in 2 hours = 724×2=712Part of the tank empty after 2 hours = 1-712=512Time taken by pipe B to fill the remaining tank = 512÷18=512×8=103=313 hours

No comments:

Post a Comment

Contact Form

Name

Email *

Message *