Exercise 9C
Question 1
6 men take 12 hours to weed a certain field. How long would 9 men take to do so, if all work at the same rate?
Sol :
M1=6 men, D1=12 , M2=9
M1.D1=M2.D2
or D2=6×129=8 hr
Question 2
12 men can hoe a field in 10 days. How long will 15 men take?
Sol :
M1=12 men, D1=10 , M2=15
M1.D1=M2.D2
or D2=12×1015=8 days
Question 3
A and B can do a piece of work in 6 and 12 days respectively. They (both) will complete the work in how many days?
Sol :
A do work in 6 days
B do work in 6 days
Question 4
Rekha can finish a work in 18 days and Prema can do the same work in half the time taken by Rekha. Then, working together, what part of the same work they can finish in a day?
Sol :
Rekha can finish a work in 18 days
∴efficiency of rekha =118
Prema can do a work in =182=9 days
∴efficiency of prema =19
Question 5
A alone can complete a work in 12 days and B alone can complete the same work in 24 days. In how many days can A and B together complete the same work?
Sol :
A can do a work =12 days
B can do a work =24 days
∴efficiency of A=112
∴efficiency of B=124
∴efficiency of (A+B)=112+124=2+124 =324=18
(A+B) do work= 8 days
Question 6
A and B together can do a piece of work in 12 days, while B alone can finish it in 30 days. In how many days can A alone finish the work?
Sol :
(A+B) do a work=12 days
∴efficiency of (A+B)=112
B can do alone a work=30 days
∴efficiency of B=130
∴efficiency of A=112−130=5−260 =360=120
Question 7
A, B and C can complete a work in 2 h. If A does the job alone in 6 h and B in 5 h, how long will it take C to finish the job alone?
Sol :
∴C can do a work =152=712 hours
Question 8
A and B can do a piece of work in 72 days. B and C can do it in 120 days. A and C can do it in 90 days. In what time can A alone do it?
Sol :
(A+B) can do a piece of work=72 days
∴(B+C) can do a piece of work=120 days
∴(A+C) can do a piece of work=90 days
∴efficiency of 2(A+B+C)=5+3+4360=12360=130
∴efficiency of (A+B+C)=130×2=160
∴efficiency of A=efficiency of (A+B+C)-efficiency of (B+C)
=160−1120=1120
∴A can do a work 120 days
Question 9
A can do a piece of work in 10 days and B in 20 days. They begin together but A leaves 2 days before the completion of the work. In how many days will the whole work be completed?
Sol :
∴efficiency of A=110
∴efficiency of B=120
Let time take be x days
∴x−210+x20=1
2(x−2)+x20=1
or 2x-4+x=20
3x=20+4
x=8 days
Question 10
Piyush and Ajit together can complete a work in 3 days. They started together but after 2 days Ajit left the work. If the work is completed after 2 more days, Piyush alone can complete it in how many days?
Sol :
∴Complete by Piyush in 6 days
Question 11
A can complete a work in 10 days, B in 12 days and C in 15 days. all of them began the work together, but A had to leave the work after 2 days of the start and B, 3 days before the completion of the work. How long did the work last?
Sol :
∴Total unit =60
Total unit divided in
A=6 unit, B=5 units, C=4 units
∴A's 2 days work=6×2=12 unit
or 2×110+x−312+x15=1
or 12+5x−15+4x60=1
or x=60+37=639=7 days
Question 12
Sanjay and Ranbir can do a piece of work in 45 and 40 days respectively. They began the work together but Sanjay leaves after some days and Ranbir finished the remaining work in 23 days. After how many days did Sanjay leave?
Sol :
∴Total work =360 {8 and 9}
Ranbir work 23 days=23×9=207 unit
∴Total work done by (Sanjay+Ranbir) together=360-207=153 units
∴Sanjay leave=1538+9=15317
=9 days
This comment has been removed by the author.
ReplyDelete