S.chand mathematics solution class 8 chapter 11 time and work

 EXERCISE 11


Q1 | Ex-11 | Cl-8 | Schand Composite Mathematics | Time and Work | Myhelper


Question 1

A can do $\dfrac{3}{4}$ of the work in 12 days . In how many days can he complete $\dfrac{1}{8}th$ of the work ?

Sol :

⇒A can do $\dfrac{3}{4}$ of work in 12 days

⇒ A can do 1 work in $12\times \dfrac{4}{3}$ days And  [Multiplying both side by 4/3]

⇒ A can do $\dfrac{1}{8}$ work in $12\times \dfrac{4}{3}\times \dfrac{1}{8}$ days [Multiplying both side by 1/8]

$=4\times \dfrac{1}{2}$ days

= 2 days

 


Q2 | Ex-11 | Cl-8 | Schand Composite Mathematics | Time and Work | Myhelper

Question 2

Tanu can do a piece of work in 24 days and Manisha can do it in 30 days . How long will they take to do the work working together ?

Sol :

⇒Tanu can do a piece of work in 24 days

⇒So Tanu's one day work $=\dfrac{1}{24}$

⇒Manisha can do the same work in 30 days

⇒So Manisha's one day work $=\dfrac{1}{30}$

⇒We know that

⇒Tanu and Manisha's one day work = Tanu's one day work + Manisha's one day work

$=\dfrac{1}{24}+\dfrac{1}{30}$ [Taking LCM]

$=\dfrac {5 + 4}{120}$

$= \dfrac{9}{120}$

$= \dfrac{3}{40}$

⇒Tanu and Manisha's one day work $= \dfrac{3}{40}$

⇒Total time required for completing work $\dfrac{1}{\text{one day work}}=\dfrac{1}{\dfrac{3}{40}}$

⇒So Tanu and Manisha can complete the same work in $= \dfrac{40}{3}=13\dfrac{1}{3}$ days.

 


Q3 | Ex-11 | Cl-8 | Schand Composite Mathematics | Time and Work | Myhelper

Question 3

A and B can polish the floors of a building in 18 days . A alone can do $\dfrac{1}{6}$ of this job in 4 days . in how many days can B alone polish the floors ?

Sol :

⇒A alone complete whole work in $=\dfrac{4}{\dfrac{1}{6}}=4\times\dfrac{6}{1}$ = 24 days

⇒A's one day work $=\dfrac{1}{24}$

⇒(A and B)'s one day work $=\dfrac{1}{18}$

⇒Also , (A+B)'s one day work = A's one day work + B's one day work

⇒$\dfrac{1}{18}=\dfrac{1}{24}+\dfrac{1}{x}$

⇒$\dfrac{4-3}{72}=\dfrac{1}{x}$

⇒$\dfrac{1}{72}=\dfrac{1}{x}$

⇒x = 72

72 days

 


Q4 | Ex-11 | Cl-8 | Schand Composite Mathematics | Time and Work | Myhelper

Question 4

A and B can weave a certain number of baskets in 12 days and 15 days respectively . They work together for 5 days and then B leaves . In how many days will A finish the rest of the work ?

Sol :

⇒A's one day work $=\dfrac{1}{12}$

⇒B's one day work $=\dfrac{1}{15}$

⇒(A + B)'s one day work = A's one day work + B's one day work

$=\dfrac{1}{12}+\dfrac{1}{15}$

$=\dfrac{5+4}{60}$

$=\dfrac{9}{60}$

$=\dfrac{3}{20}$

⇒(A + B)'s one day work $=\dfrac{3}{20}$

⇒They work together for 5 days $=5\times \dfrac{3}{20}= \dfrac{3}{4}$

⇒Remaining work $=1-\dfrac{3}{4}$

$=\dfrac{4-3}{4}=\dfrac{1}{4}$

⇒A can complete all work in 12 days . So , remaining work can be done in $=\dfrac{1}{4}\times 12$ days

= 3 days

 


Q5 | Ex-11 | Cl-8 | Schand Composite Mathematics | Time and Work | Myhelper

Question 5

A , B and C working together take 8 min . to address a pile of envelopes . A and B together would take 10 min ; A and C together would take 15 min . How long would each take working alone ?

Sol :

⇒(A + B + C)'s one unit work $=\dfrac{1}{8}$

⇒(A + B)'s one unit work $=\dfrac{1}{10}$

⇒(A + C)'s one unit work $=\dfrac{1}{15}$

⇒C's one unit work = (A + B + C)'s one unit work  - (A + B)'s one unit work

$=\dfrac{1}{8}-\dfrac{1}{10}$

$=\dfrac{5-4}{40}=\dfrac{1}{40}$

∴C alone take 40 min

⇒B's one unit work = (A + B + C)'s one unit work  - (A + C)'s one unit work

$=\dfrac{1}{8}-\dfrac{1}{15}$

$=\dfrac{15-8}{120}=\dfrac{7}{120}$

∴B alone take $\dfrac{120}{7}$ min

⇒A's one unit work = (A + B + C)'s one unit work  - B's one unit work - C's one unit work

$=\dfrac{1}{8}-\dfrac{7}{120}-\dfrac{1}{40}$

$=\dfrac{15-7-3}{120}=\dfrac{5}{120}=\dfrac{1}{24}$

∴A alone take 24 min

A→24 min ; B→$\dfrac{120}{7}$ min ; C→40 min

 


Q6 | Ex-11 | Cl-8 | Schand Composite Mathematics | Time and Work | Myhelper

Question 6

A and B can do a piece of work in 6 days and 4 days respectively . A started the work ; worked at it for 2 days and then was joined by B . Find the total time taken to complete the work .

Sol :

⇒A's one day work $=\dfrac{1}{6}$

⇒B's one day work $=\dfrac{1}{4}$

⇒A's 2 days work $=2\times \dfrac{1}{6}=\dfrac{1}{3}$

⇒Remaining work $=1-\dfrac{1}{3}$

$=\dfrac{3-1}{3}=\dfrac{2}{3}$..(i)

⇒(A+B)'s one day work = A's one day work + B's one day work

$=\dfrac{1}{6}+\dfrac{1}{4}$

$=\dfrac{2+3}{12}=\dfrac{5}{12}$

or

⇒Total time required to complete work together$=\dfrac{1}{\text{one day work}}$ $=\dfrac{1}{\dfrac{5}{12}}=\dfrac{12}{5}$

⇒Time to complete the remaining work together $=\dfrac{2}{3}\times \dfrac{12}{5}$ $=\dfrac{8}{5}$..(ii)

⇒Total time required to complete work = A's alone working time + (A+B)'s working together time

$=2+\dfrac{8}{5}$

$=\dfrac{10+8}{5}$

$=\dfrac{18}{5}=3\dfrac{3}{5}$

 


Q7 | Ex-11 | Cl-8 | Schand Composite Mathematics | Time and Work | Myhelper

Question 7

780 is paid for a task which A can do in 6 days , B in 8 days and C in 4 days . If all work together , how much money should each receive ?

Sol :

⇒A's one day work $=\dfrac{1}{6}$

⇒B's one day work $=\dfrac{1}{8}$

⇒C's one day work $=\dfrac{1}{4}$

∴Ratio of shares of money of A , B and C = Ratio of their one day work

$=\dfrac{1}{6}:\dfrac{1}{8}:\dfrac{1}{4}$ $=\dfrac{1}{6}\times 24:\dfrac{1}{8}\times 24 :\dfrac{1}{4}\times 24$ [L.C.M of 6 , 8 and 24]

= 4 : 3 : 6

∴Sum of the ratios = 4 + 3 + 6 = 13

⇒A's share $=\dfrac{4}{13}\times 780$ = 240

⇒B's share $=\dfrac{3}{13}\times 780$ = 180

⇒C's share $=\dfrac{6}{13}\times 780$ = 360

A→240 , B→180 , C→360

 ALTERNATE METHOD

⇒A's one day work $=\dfrac{1}{6}$

⇒B's one day work $=\dfrac{1}{8}$

⇒C's one day work $=\dfrac{1}{4}$

Total work done$=\dfrac{1}{6}+\dfrac{1}{8}+\dfrac{1}{4}$

$=\dfrac{4+3+6}{24}=\dfrac{13}{24}$

∴Shares of money of A , B and C = Ratio of their one day work / Total work × Total money

⇒A's share $\dfrac{\frac{1}{6}}{\frac{13}{24}}\times 780$

$=\dfrac{4}{13}\times 780$ = 240

⇒B's share $\dfrac{\frac{1}{8}}{\frac{13}{24}}\times 780$

$=\dfrac{3}{13}\times 780$ = 180

⇒C's share $\dfrac{\frac{1}{4}}{\frac{13}{24}}\times 780$

$=\dfrac{6}{13}\times 780$ = 360

A→240 , B→180 , C→360



Q8 | Ex-11 | Cl-8 | Schand Composite Mathematics | Time and Work | Myhelper

Question 8

X works thrice as fast as Y . If Y alone can complete a job in 18 days , find how ,many days will X and Y together take to complete the job .

Sol :

⇒Y's one day work $=\dfrac{1}{18}$

A.T.Q

⇒3X=Y

⇒$X=\dfrac{Y}{3}$

⇒$X=\dfrac{18}{3}$

⇒X=6

⇒X's one day work $=\dfrac{1}{6}$

⇒(X+Y)'s one day work = X's one day work + Y's one day work

$=\dfrac{1}{6}+\dfrac{1}{18}$

$=\dfrac{3+1}{18}=\dfrac{4}{18}=\dfrac{2}{9}$

⇒Total time required by (X+Y) to complete work $=\dfrac{1}{\text{one day work}}$ $=\dfrac{1}{\dfrac{2}{9}}$ $=\dfrac{9}{2}$ or $=4\dfrac{1}{2}$ days

 


Q9 | Ex-11 | Cl-8 | Schand Composite Mathematics | Time and Work | Myhelper

Question 9

A can do a job in 20 days , B in 30 days and C in 60 days . If A is helped by B and C on every third day , then in how many days will the job be finished ?

Sol :

⇒A's one day work $=\dfrac{1}{20}$..(i)

⇒(A+B+C)'s one day work = A's one day work + B's one day work + C's one day work

$=\dfrac{1}{20}+\dfrac{1}{30}+\dfrac{1}{60}$

$=\dfrac{3+2+1}{60}$

$=\dfrac{6}{60}=\dfrac{1}{10}$..(i)

⇒According to question, A work starting two days alone and on every third day all together work .

Total time to complete work = 1st day + 2nd day + 3rd day

1 and 2 day equal to (i) and 3 day equal to (ii)

$=\dfrac{1}{20}+\dfrac{1}{20}+\dfrac{1}{10}$

$=\dfrac{1+1+2}{20}=\dfrac{4}{20}=\dfrac{1}{5}$

Which means in 3 days 1/5 work is completed

$\text{3 days}=\dfrac{1}{5}\text{ work}$

$3\times 5 = 1 \text{ work}$

= 15 days to complete whole work

 


Q10 | Ex-11 | Cl-8 | Schand Composite Mathematics | Time and Work | Myhelper

Question 10

Sonia can copy 50 pages in 10 hours . Priya and Sonia can copy 300 pages in 40 hours . In how much time can Priya copy 30 pages ?

Sol :

⇒Sonia in 10 hours can copy 50 pages

∴In 1 hour sonia can copy $\dfrac{50}{10}=\dfrac{5}{1}$ pages

⇒Priya and Sonia together in 40 hours can copy 300 pages

∴Priya and Sonia together in 1 hours can copy $\dfrac{300}{40}=\dfrac{30}{4}$ pages

⇒Priya's 1 hour work = Priya and Sonia together in 1 hours work - Sonia's 1 hour work

$=\dfrac{30}{4}-\dfrac{5}{1}$

$=\dfrac{30-20}{4}=\dfrac{10}{4}=\dfrac{5}{2}$

⇒Number of hours required to complete the work $=\dfrac{\text{Work to be done}}{\text{one day work}}$

$=\dfrac{30}{\dfrac{5}{2}}$

$=5\times\dfrac{2}{5}$

= 12 hours

 


Q11 | Ex-11 | Cl-8 | Schand Composite Mathematics | Time and Work | Myhelper

Question 11

A tap can fill a cistern in 15 minutes and another can empty it in 18 minutes . Find in how many minutes the tank will be filled up ?

Sol :

⇒Tank filled by tap in one hour $=\dfrac{1}{15}$ part

⇒Tank empty by tap in one hour $=\dfrac{1}{18}$ part

⇒Tank filled in one hour when both taps are open $=\dfrac{1}{15}-\dfrac{1}{18}$

$=\dfrac{6-5}{90}=\dfrac{1}{90}$

= 90 mins the tank will be filled up

 


Q12 | Ex-11 | Cl-8 | Schand Composite Mathematics | Time and Work | Myhelper

Question 12

Two taps can fill a cistern in 15 hours and 20 hours respectively . A third tap can empty it in 30 hours . How long will they take to fill the cistern if all the taps are opened ?

Sol :

⇒Tank filled by first tap in one hour $=\dfrac{1}{15}$ part

⇒Tank filled by second tap in one hour $=\dfrac{1}{20}$ part

⇒Tank empty by third tap in one hour $=\dfrac{1}{30}$ part

⇒Tank filled in one hour when all three taps are open $=\dfrac{1}{15}+\dfrac{1}{20}-\dfrac{1}{30}$

$=\dfrac{4+3-2}{60}=\dfrac{5}{60}=\dfrac{1}{12}$

= 12 hours take the tank to fill up

 


Q13 | Ex-11 | Cl-8 | Schand Composite Mathematics | Time and Work | Myhelper

Question 13

Two taps running together can fill a bath in 4 minutes , which is filled by one of the taps by itself in 7 minutes . How long would it take if the other pipe is running by itself ?

Sol :

⇒Bathtub filled by (1st + 2nd) taps in one hour $=\dfrac{1}{4}$ part

⇒Bathtub filled by first tap in one hour $=\dfrac{1}{7}$ part

⇒Bathtub filled by (1st + 2nd) taps in one hour = time taken by 1st tap in one hour + time taken by 2nd tap in one hour

⇒$\dfrac{1}{4}=\dfrac{1}{7}+x$

⇒$\dfrac{1}{4}-\dfrac{1}{7}=x$

⇒$\dfrac{7-4}{28}=x$

⇒$x=\dfrac{3}{28}$

Time taken by Second tap $=\dfrac{28}{3}=9\dfrac{1}{3}$ minutes

 


Q14 | Ex-11 | Cl-8 | Schand Composite Mathematics | Time and Work | Myhelper

Question 14

A cistern can be filled by 3 taps A, B and C when turned on separately in 12 min , 10 min and 15 min respectively . If all are turned on together for $2\dfrac{2}{3}$ minutes and if B and C are then turned off , how much time will A alone take to fill the cistern ?

Sol :

⇒Time taken when all 3 taps are open for a unit time = Tap A open for unit time + Tap B open for unit time + Tap C open for unit time

$=\dfrac{1}{12}+\dfrac{1}{10}+\dfrac{1}{15}$

$=\dfrac{5+6+4}{60}=\dfrac{15}{60}=\dfrac{1}{4}$

A.T.Q

⇒All are turned for $2\dfrac{2}{3}$ minutes $=\dfrac{1}{4}\times 2\dfrac{2}{3}$ $=\dfrac{1}{4}\times \dfrac{8}{3}=\dfrac{2}{3}$

⇒Remaining cistern to be filled $=1-\dfrac{2}{3}$ $=\dfrac{3-2}{3}=\dfrac{1}{3}$

⇒Tap A alone fill the remaining cistern [1/3 of 12min] $=\dfrac{1}{3}\times 12$

= 4 minutes

 


 

6 comments:

  1. please send mcqs and challenge questions also

    ReplyDelete
  2. aapne right click disable kyu kiya hai

    ReplyDelete
  3. HI! This is a very helpful website for the students who want to cheat in exam. Just kidding very helpful website, and very helpful for me.
    Thanks!

    ReplyDelete

Contact Form

Name

Email *

Message *